Our regional super hub is nearing the half way stage with the majority of the internal fit-out complete, permitted development status granted and plans progressing with connectivity. 

Preliminary works on the point of presence is now complete and work is progressing on connecting backhaul. We have surveyed a 700m route to connect fibre optic cabling to serve gigabit capable broadband via fixed wireless access. 

Further work will be carried out to survey the local area to connect full fibre and enabling longer range antenna to be used to connect even more homes and businesses to faster broadband. This Point of Presence and duct route is open to wholesale and will provide a another option for this part of rural Somerset.

Please see www.westwifi.co.uk for more information.